In SAP PM, which of the following is not possible after the Maintenance Order is set with 'TECO' ?
(only one answer)
A) Change the Settlement Receiver.
B) Perform Goods Receipt of Non-Stock Purchase Order.
C) Invoice variances compared to Purchase Order will be absorbed to the Maintenance Order.
D) Overhead calculation.
E) Reverse the 'TECO' status back to 'REL' status.
.
(only one answer)
A) Change the Settlement Receiver.
B) Perform Goods Receipt of Non-Stock Purchase Order.
C) Invoice variances compared to Purchase Order will be absorbed to the Maintenance Order.
D) Overhead calculation.
E) Reverse the 'TECO' status back to 'REL' status.
.
Answer: B
ReplyDeleteGood Receipt for Non-stock Purchase Order, External Operation, and Service Entries are not allowed after TECO.