Question no 2079 : Costing Sheet

In SAP CO, the Costing Sheet is directly assigned to which of the following ?

(only one answer)

A)    Order type Plant independent parameter.
B)    Order type Plant dependent parameter.
C)    Costing Variant.
D)    Valuation Variant.
E)    Controlling Area.
.

1 comment:

  1. The Costing Sheet is assigned to the Valuation Variant which in turn is assigned to the Costing Variant and then finally the Costing Variant is assigned to the Order type Plant Dependent Parameter.

    ReplyDelete