In SAP Plant Maintenance ECC6.0, when performing a goods issue with reference to an Order (example: Maintenance Order), what do you expect ?

(more then one answers)

A)    The movement type is defaulted from the Maintenance Order.
B)    You will be able to see the Reservation number in the MIGO item detail.
C)    You can opt to set the "Final issue" indicator to the Reservation item.
D)    The quantity issue will be checked against the upper tolerance limit set in the Maintenance Order.
E)    The Maintenance Order must be set with the "REL" (Release status) for the goods issue to take place.
.

1 comment:

  1. D) Unfortunately as of ECC6.0 EhP4, there are no tolerance limit possible for goods issue with reference to reservations automatically generated or manually created.