In SAP QM ECC6.0, the Material Specification master data demonstrates which of the following characteristics ?
(more then one answers)
A) New Inspection characteristics can also be created when creating the material specification.
B) You can assign the Master Inspection characteristics as a "Reference characteristics" or "Copy complete model" in the material specification.
C) In the product structure (transaction CC04), the material specification is also displayed in addition to the inspection task lists.
D) The final step of the material specification creation is to assign the it to the plants which will be using it.
E) Dynamic modification can be optionally assigned to the header of the material specification.
.
(more then one answers)
A) New Inspection characteristics can also be created when creating the material specification.
B) You can assign the Master Inspection characteristics as a "Reference characteristics" or "Copy complete model" in the material specification.
C) In the product structure (transaction CC04), the material specification is also displayed in addition to the inspection task lists.
D) The final step of the material specification creation is to assign the it to the plants which will be using it.
E) Dynamic modification can be optionally assigned to the header of the material specification.
.
Answer: B, C
ReplyDeleteThe material specification does not have a header; therefore dynamic modification cannot be assign to the material specification this way.
ReplyDeleteYou enter the plant and inspection characteristics for a material specification in the interface table provided and not assign the material specification to several plants.
ReplyDeleteYou can only assign existing or pre-created Master inspection characteristics (MIC) to the material specification. When assigning the MIC, you can set it as either "Reference Characteristics" or "Copy complete model" to the inspection lot.