This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, July 15, 2012

Question no 1615: Maintenance Plan for External Services

In SAP PM ECC6.0, the characteristics of Maintenance Plan for External Services are ?

(more then one answers)

A)   After approval of the Service Entry Sheet, the costs are debited into the Cost Center assigned in the Maintenance Plan.
B)   On maintenance due, Service Entry Sheet is generated against the Framework Purchase Order.
C)   The General Ledger for the Expenses account to be debited at approval of the Service Entry Sheet is defaulted from the Technical Object assigned in the Maintenance Plan.
D)   After approval of the Service Entry Sheet, the costs are debited into the Settlement Order assigned in the Maintenance Plan.
E)   A Purchase Order document type is entered in the Maintenance Plan for the Framework Order creation when maintenance is due.
.

3 comments:

  1. A) cost are debited to the settlement maintenance order assigned to the maintenance plan.

    ReplyDelete
  2. C) the general ledger for the consumption or expenses account upon service entry sheet approval is from the maintenance plan.

    ReplyDelete
  3. E) there are no document types to be entered in the maintenance plan of this scenario.

    ReplyDelete