This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Saturday, August 6, 2011

Question no 1330 : Component Allocation

In SAP PP, which of the following statement is correct about Component Allocation/Assignment ?

(more then one answers)

A)     Component allocation to the Routing Operations is not mandatory for MRP Execution.
B)      The Routing is always be ignored in an MRP run if Components are not allocated to Routing Operations.
C)      When Components are not allocated to the Routing Operations, the Production Order creation is not possible.
D)      When Components are not allocated to the Routing Operations, the Production Order creation will assign all components to the first operation.
E)       A BOM component item cannot be allocated to more then one Routing Operation.
.

2 comments:

  1. B) if you select to use lead time scheduling at MRP run, the system will always try to look for the Routing regardless of whether any component allocation to the routing operations.

    ReplyDelete
  2. C) There can be an operation default from the IMG when routing is not found at production order creation.

    ReplyDelete

Note: Only a member of this blog may post a comment.