In SAP MM and PP, assume the following data and determine the source determination ?
Material master is assigned with Lot Sizing "EX".
Quota for Vendor A : 2, Allocated Qty : 100, Quota-Based Qty : 0
Quota for Vendor B : 1, Allocated Qty : 200, Quota-Based Qty : 0
Quota for Vendor C : 3 , Allocated Qty: 500, Quota-Based Qty : 1000
There is a new requirement of 400,
what is the correct source determination ?
A) Vendor A
B) Vendor B
C) Vendor C
D) Quantity is split between Vendor A, B, C
E) Quantity is split between Vendor A and B.
.
Material master is assigned with Lot Sizing "EX".
Quota for Vendor A : 2, Allocated Qty : 100, Quota-Based Qty : 0
Quota for Vendor B : 1, Allocated Qty : 200, Quota-Based Qty : 0
Quota for Vendor C : 3 , Allocated Qty: 500, Quota-Based Qty : 1000
There is a new requirement of 400,
what is the correct source determination ?
A) Vendor A
B) Vendor B
C) Vendor C
D) Quantity is split between Vendor A, B, C
E) Quantity is split between Vendor A and B.
.
Answer: A
ReplyDelete