Question no : 169 PP/PM/CS Work Center Available Capacity Calculation

In SAP PP/PM/CS, Determine the daily available capacity from the following capacity details:

Start time : 08:00
Finish time : 17:00
Break time : 01:00
Number of capacity : 5
Utilization : 90%

A) 8 hours
B) 40 hours
C) 36 hours
D) 45 hours
E) 40.5 hours
.

1 comment:

  1. Available Capacity
    = ((Finish Time - Start Time) - Break Time) x no. of capacity x utilization / 100
    = ((17 - 8) - 1) x 5 x 90/100
    = 8 x 5 x 90/100
    = 40 x 90/100
    = 3600/100
    = 36