In SAP PP/PM/CS, Determine the daily available capacity from the following capacity details:
Start time : 08:00
Finish time : 17:00
Break time : 01:00
Number of capacity : 5
Utilization : 90%
A) 8 hours
B) 40 hours
C) 36 hours
D) 45 hours
E) 40.5 hours
.
Start time : 08:00
Finish time : 17:00
Break time : 01:00
Number of capacity : 5
Utilization : 90%
A) 8 hours
B) 40 hours
C) 36 hours
D) 45 hours
E) 40.5 hours
.
Available Capacity
ReplyDelete= ((Finish Time - Start Time) - Break Time) x no. of capacity x utilization / 100
= ((17 - 8) - 1) x 5 x 90/100
= 8 x 5 x 90/100
= 40 x 90/100
= 3600/100
= 36