This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, March 14, 2010

Question no : 168 MM Purchasing Contract Basics

Which of the following is true about Contract documents in MM ?

I) It can be created without Plant.
II) Account assignments are not allowed.
III) You can copy a contract form another contract.
IV) Good receipt is not possible against a contract.
V) A scheduling agreement can be crate reference to a contract.

A) I, II, III
B) I, III
C) II, III, V
D) I, III, V
E) II, III, IV, V
.

1 comment:

Note: Only a member of this blog may post a comment.