This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Wednesday, April 15, 2009

Question no : 124 CO Production Costing Valuation Variant

In SAP CO, The Valuation Variant in the Costing Variant allows you to determine which of the following costs ?

I)    Material Cost.
II)   Activity Based Cost.
III)  Subcontracting Cost.
IV)  Operation Cost.
V)   Mix Cost Structure from 2 BOMs.

A)   I, II, IV
B)   I, IV
C)   I, II, III, IV
D)   I, III, IV
E)   I, II, III, IV, V
.

2 comments:

  1. A valuation variant that contains the required parameters for the valuation of a cost estimate.
    The following strategies are available:
    . Material valuation
    . Activity Types / Processes
    . Subcontracting
    . External processing
    . Link to Costing Sheet for Overhead Cost calculation

    ReplyDelete