This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, February 21, 2010

Question no : 120 PP Planning MRP and Scheduling Agreement

In SAP PP/MM, Which master data setup is required when the automatic generation of delivery schedule against the scheduling agreement is required from the MRP run ?

A)    Quota arrangement.
B)    Purchasing info record.
C)    Scheduling agreement.
D)    Source list.
E)    Auto delivery schedule indicator in the vendor master.
.

1 comment:

Note: Only a member of this blog may post a comment.