Question 4112 : Cost Estimate with Quantity Structure

In SAP Controlling for Product Cost Planning as at S/4 1909, which of the following determines if a Material can proceed with Qty Structure Cost Estimate ?

(only one answer)

A) Material created with a Material Type set with "Costing with Qty Structure".
B) Material created with a Material Group set with "Costing with Qty Structure".
C) User parameter set with "Costing with Qty Structure".
D) Costing Variant assigned in the Costing view in the Material Master.
E) Material assigned with a Production Version set with "Costing with Qty Structure" in the MRP 4 view. 
.

Answer: A

In OMS2 Material Type configuration, you can find an indicator "With Qty Structure" which is required to be switched on if the Material is to be allowed for Costing with Quantity Structure.