In SAP for Material Management or PP as at S/4 1909, the Simplification result of Material Master MRP4 view now without Storage Location segment. One of the Pre-requisites of the Control Cycle Creation for Kanban Containers is that the Storage Location must be excluded from Planning; how can this be achieved ?
(only one answer)
A) Storage Location master in the Configuration to set without Planning.
B) use MMSC to set No Planning for the Storage Location.
C) The indicator of "No Planning" can be found in the Control Cycle Header.
D) The indicator of "No Planning" can be found in the Production Supply Area.
E) Set MRP Type "ND" in the relevant MRP Area in the Material Master.
Answer: E
The Kanban Storage Location is assigned to PSA and MRP Area. Extend the Material Master to MRP Area with MRP Type "ND"
(only one answer)
A) Storage Location master in the Configuration to set without Planning.
B) use MMSC to set No Planning for the Storage Location.
C) The indicator of "No Planning" can be found in the Control Cycle Header.
D) The indicator of "No Planning" can be found in the Production Supply Area.
E) Set MRP Type "ND" in the relevant MRP Area in the Material Master.
Answer: E
The Kanban Storage Location is assigned to PSA and MRP Area. Extend the Material Master to MRP Area with MRP Type "ND"