In SAP MRP Planning as at ECC6 EhP8, which of the following Lot Size key is recommended to always split the requirements between Suppliers or Production Versions based on the Quota entered for the Supplier or Production Versions in the Quota Arrangement ?
(only one answer)
A. EX
B. ES
C. FX
D. FS
E. SP
.
Answer: B
"ES" Lot for Lot with Split
(only one answer)
A. EX
B. ES
C. FX
D. FS
E. SP
.
Answer: B
"ES" Lot for Lot with Split
The same functionality is available as in the current S/4HANA2023 version.