In SAP PM as at ECC6.0 EhP6, which of the following is used to default the Activity Type in the Operation of the Maintenance Order ?
(only one answer)
A) Order Type.
B) Work Center.
C) Planning Plant.
D) Equipment.
E) Functional Location.
.
Answer: B
Work Center defaults.
(only one answer)
A) Order Type.
B) Work Center.
C) Planning Plant.
D) Equipment.
E) Functional Location.
.
Answer: B
Work Center defaults.