In SAP PM as at ECC6.0 EhP6, which of the following are the characteristics of a Multi-Counter Plan ?
(more than one answers)
A) Counters are necessary for performance based UOM Cycles.
B) Cycle Set for the Task List assigned to the Multi-Counter Plan must match the Cycle Set assigned to the header of the Multi-Counter Plan.
C) Cycle Set is created with different unit of measure cycles.
D) The Strategy is only for Equipment Masters and not Functional Locations.
E) A General Task List without any Strategy can be used for the Multi-Counter Plan.
.
click "1 comment" for suggested answer
(more than one answers)
A) Counters are necessary for performance based UOM Cycles.
B) Cycle Set for the Task List assigned to the Multi-Counter Plan must match the Cycle Set assigned to the header of the Multi-Counter Plan.
C) Cycle Set is created with different unit of measure cycles.
D) The Strategy is only for Equipment Masters and not Functional Locations.
E) A General Task List without any Strategy can be used for the Multi-Counter Plan.
.
click "1 comment" for suggested answer
Answers: A, C, E
ReplyDeleteA multiple counter plan is used in counter-based (performance-based) maintenance. This type of maintenance planning is not based on a maintenance strategy. This means that you create a multiple counter plan without a maintenance strategy .
In the multiple counter plan you create maintenance cycles and allocate counters of equipment or functional locations with different dimensions to them, for example, flight hours, number of take-offs and landings, kilometers travelled. You can also integrate time-based cycles into the maintenance plan. However, these do not have counters. Alternatively, you can also create a multiple counter plan with a cycle set as a copy model for maintenance cycles.