In SAP PP as at ECC6.0 EhP6, which of the following are not possible for PP Production Order ?
(more than one answers)
A) Production Campaign.
B) PP Sheet. (similar to PI sheet)
C) Use of Production Version.
D) Backflushing.
E) CATS entry for Confirmation.
.
click "1 comment" for suggested answers
(more than one answers)
A) Production Campaign.
B) PP Sheet. (similar to PI sheet)
C) Use of Production Version.
D) Backflushing.
E) CATS entry for Confirmation.
.
click "1 comment" for suggested answers
Answers: A, B, E
ReplyDeleteA) Production Campaign is for PPPI
B) PI sheet is for PPPI
C) Prodution Version for both PPDI and PPPI
D) Backflushing is mandatory for REM and optional for PPDI and PPPI
E) CATs entry for Confirmation cannot yet be used for PP