In SAP PP as at ECC6.0 EhP6, which of the following is included in the MRP Mechanics Scheduling step ?
(more than one answer)
A) Goods Receipt Time.
B) Opening Date.
C) Planned Delivery Time.
D) Safety Time.
E) Safety Stock.
.
Answer: A, B, C, D
(more than one answer)
A) Goods Receipt Time.
B) Opening Date.
C) Planned Delivery Time.
D) Safety Time.
E) Safety Stock.
.
Answer: A, B, C, D