Question no 3675 : Repetitive Manufacturing

In SAP PP as at ECC6.0 EhP6, which of the following are correct about Repetitive Manufacturing ?

(more than one answers)

A)  REM Planned Orders can be generated via MRP Run.
B)  Goods Issue and Goods Receipt is possible with reference to a REM Planned Orders.
C)  REM Planned Orders can collect costs just like a Production Orders.
D) BOM and Routing are optional in Repetitive Production Version.
E)  REM Planned Orders can be viewed in the Stocks Requirements Lists.
.
Click "1 comment" for Suggested answers

1 comment:

  1. Answers: A, B, E

    C) REM Planned Costs cannot collect costs, cost is collected via a Cost Collector.

    D) BOM and Routing should be assigned in the Production Version for Logistics and Costing reasons.