In SAP PP as at ECC6.0 EhP7, which of the following can MRP Generate ?
(more than one answers)
A) Purchase Requisition.
B) Purchase Order.
C) Delivery Schedule for Scheduling Agreement.
D) Planned Order.
E) RFQ.
.
click "1 comment" to display possible Solution
(more than one answers)
A) Purchase Requisition.
B) Purchase Order.
C) Delivery Schedule for Scheduling Agreement.
D) Planned Order.
E) RFQ.
.
click "1 comment" to display possible Solution
Answers: A, C, D
ReplyDeleteMRP can generate Purchase Requisitions, Delivery Schedule against an existing Scheduling Agreements registered in a Source List and Planned Orders ONLY
Any other Purchasing Documents such as PO, RFQ, Quotation, Contract or Scheduling Agreements cannot be generated by the MRP Run.