Question no 3656 : Maintenance Item

In SAP PM as at ECC6.0 EhP6, which of the following can have only one Maintenance Item ?

(only one answer)

A)  Single-Cycle Plan when the calling object is a Maintenance Notification.
B)  Single-Cycle Plan when the calling object is a Maintenance Order.
C)  Single-Cycle Plan when the calling object is a Inspection Lot.
D)  Single-Cycle Plan when the calling object is a Service Entry Sheet. 
E)  Single-Cycle Plan when the calling object is a Purchase Order.
.

Answer: D