In SAP PM as at ECC6.0 EhP6, which of the following can collect costs in PM ?
(more than one answers)
A) Maintenance Notification.
B) Maintenance Order.
C) Maintenance Plan.
D) Maintenance Item.
E) Equipment.
.
Answer: B
Only the MO can collect costs in the PM Module.
(more than one answers)
A) Maintenance Notification.
B) Maintenance Order.
C) Maintenance Plan.
D) Maintenance Item.
E) Equipment.
.
Answer: B
Only the MO can collect costs in the PM Module.