In SAP MM as at ECC6.0 EhP6, which of the following Purchasing Document can be created without a Plant ?
(more than one answers)
A) Purchase Requisition.
B) RFQ.
C) Purchase Order.
D) Contract.
E) Scheduling Agreement.
.
Answer: B, D
Both RFQ and Contract can be created without a Plant.