In SAP MM as at ECC6.0 EhP6, which of the following in MM has validity periods ?
(ore than one answers)
A) Source List.
B) Purchasing Info Record General Data.
C) Purchasing Info Record Condition Record.
D) Quota Arrangement.
E) Material Master MRP data view.
.
Answer: A, C, D
A) Goto ME01, each source list entered for a Material/Plant combination must have a valid period.
B, C) Goto ME11, the General and Purchasing Data views do not have valid period but the Condition TAB data will have valid period.
D) Goto MEQ1, the Quota Arrangement header has a valid period.
E) In General, the Material Master do not have a valid period of from-to, although you have create/change a Material with a date, and the material status entered can have a valid from date. (Hiwever, there are two related schedule change Material Master t-code MM12 and the MM13 to Activate the Changes)
In this case, you can make an argument of the answer should be A, C, D, E but I decided to be A, C, D.
(ore than one answers)
A) Source List.
B) Purchasing Info Record General Data.
C) Purchasing Info Record Condition Record.
D) Quota Arrangement.
E) Material Master MRP data view.
.
Answer: A, C, D
A) Goto ME01, each source list entered for a Material/Plant combination must have a valid period.
B, C) Goto ME11, the General and Purchasing Data views do not have valid period but the Condition TAB data will have valid period.
D) Goto MEQ1, the Quota Arrangement header has a valid period.
E) In General, the Material Master do not have a valid period of from-to, although you have create/change a Material with a date, and the material status entered can have a valid from date. (Hiwever, there are two related schedule change Material Master t-code MM12 and the MM13 to Activate the Changes)
In this case, you can make an argument of the answer should be A, C, D, E but I decided to be A, C, D.
No comments: