This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Thursday, June 21, 2018

Question no 3550 : Calling Maintenance Notifications

In SAP PM as at ECC6.0 EhP6, note the SAP Menu, which of the following Maintenance Plan transactions creates Maintenance Notification when Scheduled ?

(more than one answers)

A)  IP41 Single Cycle Plan.
B)  IP42 Strategy Plan.
C)  IP43 Multiple Counter Plan.
D)  IP40 For Service Procurement.
E)  IP50 For Contract Item.
.

Answer: A, B, C

A, B, C) will call Maintenance Notification depending on MP Category select.
D) calls Service Entry Sheet.
E) IP50 is for Customer Service, therefore it can call Service Notification or Service Order



No comments:

Post a Comment

Note: Only a member of this blog may post a comment.