In SAP PM as at ECC6.0 EhP6, which of the following method is used to ensure the Maintenance Orders are automatically assigned to the Network Activities in MEB ?
(more than one answers)
A) Ref PM/PS Element at the Task List Header.
B) Ref PM/PS Element at the Task List Operations.
C) Ref PM/PS Element at the Task List WBS.
D) Ref PM/PS Element at the Task List Network Activity.
E) Ref PM/PS Element at the Task List Revision Header.
.
Answer: A, D
Task Lit Header's + Network Activity must have matching Ref PM/PS Element.