In SAP PM as at ECC6.0 EhP6, the Permit Master is created with which of the following Organizational Structure Element ?
(only one answer)
A) Planning Plant.
B) Planning Plant + User.
C) Planning Plant + Equipment/FL Category.
D) Maintenance Plant.
E) None.
.
Answer: E
No Org Structure is required, only Permit Category
(only one answer)
A) Planning Plant.
B) Planning Plant + User.
C) Planning Plant + Equipment/FL Category.
D) Maintenance Plant.
E) None.
.
Answer: E
No Org Structure is required, only Permit Category