In SAP PM as at ECC6.0 EhP7, which Order Type and Control Key is recommended for Subcontracting of Refurbishment ?

(only one answer)

A)  Order Type PM04 with Operation Control Key PM01.
B)  Order Type PM04 with Operation Control Key PM02.
C)  Order Type PM01 with Operation Control Key PM01.
D)  Order Type PM01 with Operation Control Key PM02.
E)  Either Order Type PM01 or PM04 with Operation Control Key PM02.
.

1 comment:

  1. Answer: D

    Internal Refurbishment is to used Order Type PM04 with Operation Control Key PM01.
    Subcontracting Refurb is to used Order Type PM01 with Operation Control Key PM02.