In SAP ECC6.0 LE-Transportation, how are the Status sequenced in the "Dates" section as seen in the Shipment Document in the Standard SAP System ?
1. Check-in
2. Planned
3. Shipment Start
4. Loading End
5. Shipment End
6. Shipment Completion
7. Loading Start
A) 2, 1, 7, 4, 3, 5, 6
B) 1, 2, 7, 4, 6, 3, 5
C) 2, 7, 1, 4, 6, 3, 5
D) 1, 2, 7, 4, 3, 5, 6
E) 2, 1, 7, 4, 6, 3, 5
.
1. Check-in
2. Planned
3. Shipment Start
4. Loading End
5. Shipment End
6. Shipment Completion
7. Loading Start
A) 2, 1, 7, 4, 3, 5, 6
B) 1, 2, 7, 4, 6, 3, 5
C) 2, 7, 1, 4, 6, 3, 5
D) 1, 2, 7, 4, 3, 5, 6
E) 2, 1, 7, 4, 6, 3, 5
.
You cannot change this sequence as displayed on the segment in the Shipment Document.
ReplyDelete