In SAP MM and PP, assume the following data and determine the source determination during an MRP Run for the requirement quantity of 1200 ?
Material master is assigned with Lot Sizing "ES".
Quota for Vendor A : 1, Allocated Qty : 200, Quota-Based Qty : 0, minimum Lot Size : 1300
Quota for Vendor B : 2, Allocated Qty : 400, Quota-Based Qty : 0, minimum Lot Size : 1300
Quota for Vendor C : 3 , Allocated Qty: 600, Quota-Based Qty : 0, minimum Lot Size : 1300
Minimum to Split is 1500
Deduce the correct statement from below.
(only one answer)
A) A supply is created for Vendor A for the quantity of 1200.
B) A supply is created for Vendor B for the quantity of 1200.
C) A supply is created for Vendor C for the quantity of 1200.
D) 3 supplies created, Vendor A gets 200, Vendor B gets 400, Vendor C gets 600.
E) A supply is created for Vendor C for the quantity of 1300.
.
Answer: E