In SAP MM Purchasing's Scheduling Agreement, select the features correctly describe document type "LP" and "LPA" ?
(more the one answers)
A) "LP" will have only delivery schedule and forecast schedule as forecast schedule is always allowed.
B) "LP" will have only delivery schedule.
C) It is possible to use "LPA" for a material to have just the delivery schedule and forecast schedule.
D) The Creation Profile is only valid for "LPA" and not for "LP" arrangements.
E) For "LPA", a message output for Forecast schedule and another message output for JIT schedule is possible.
.