This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, February 6, 2011

Question no 955 : Production order concepts

In SAP PP, the production of an assembly to the finished goods is required but the stocking point for the assembly is not necessary as the production completion of the assembly is required as direct input to the final assembly. However the production order for the assembly is required. Which of the following production order concept is required through special procurement key to be used for the assembly ?

(only one answer)

A)    Phantom assembly.
B)    Collective order.
C)    Production in another Plant.
D)    Stock transfer from another assembly.
E)    Assembly order.
.

1 comment:

Note: Only a member of this blog may post a comment.