Question no : 513 PP MRP Mechanics

TERP10 Unit 4 Material Planning
Which of the following depict the correct mechanical steps of an MRP run ?

I)    Net requirement Calculation.
II)   Lot sizing Rule.
III)  BOM explosion.
IV)  Scheduling.
V)   Procurement type. 

A)   III, II, I, IV, V. 
B)   I, II, V, IV, III. 
C)   I, II, III, IV, V. 
D)   III, I, II, IV, V. 
E)    I, II, IV, III, V. 