Question no : 511 PP MRP Mechanics MRP run

TERP10 Unit 4 Material Planning
An MRP run cannot generate which of the following MRP elements ? 

I)    Purchase Requisition. 
II)   Purchase Order.
III)  Production Order.
IV)  Schedule Lines. 
V)   Contract. 

(Select ONE best answer)

A)   V only. 
B)   III, V. 
C)   III, IV, V. 
D)   II, III, V. 
E)    I, II, III, IV, V. 