Question no : 408 PP MRP Mechanics

TERP10 Quiz Unit 04 Material Planning

The _______________ controls how a material is to be procured (for example in-house production or external procurement).

A)    Material type. 
B)    MRP type. 
C)    Lot sizing procedure.
D)    Procurement type. 
E)    Production procedure. 