TERP10 Unit 13 Management Accounting
In a cost estimate with Quantity Structure, during the cost estimate run; the system will look for the relevant master data before the cost roll-up takes place. What are the Quantity Structure referring to ?
(Select ONE best answer)
A) Material, Work Center
B) Bills of Material, Routing.
C) Price Control, Cost Center.
D) Routing, Cost Center.
E) Material, Cost Center.
.
Answer: B
ReplyDeleteIn SAP costing terms Quantity Structure is referred to:
ReplyDelete. PP as the Bills of Material and Routing
. PI as the Recipe