Question no : 240 PP MRP Mechanics

In SAP PP, which of the following field allows the "Requirement quantities of dependent materials are grouped together during MRP run": 


A)    A specific lot-sizing key in the MRP 1 view of the material master.
B)    The AV check group field int he MRP 3 view of the material master.
C)    A Make-to-Order strategy in the MRP 3 view of the material master. 
D)    The Stock-determination Group field in the MRP 2 view of the material master.
E)     The individual/collective field in the MRP 4 view of the material master.
.