Question no : 70 PP MRP "NEUPL"

Which of the following planning run transactions can be used for "NEUPL" ?

I)    Single-Item-Single-Level MRP run.
II)   Single-Item-Multi-Level MRP run.
III)  On-line MPR run at the Plant level.
IV)  Background MRP run at the Plant level.
V)   Interactive MRP run.

A)   I, II, III
B)   III, IV
C)   IV
D)   V
E)    I, II, III, IV, V