Question no: 48 PP Planning Strategy 11

Strategy group 11 contains which of the following characteristics ?

I)    Stocks are not included in MRP run.
II)   Only quality inspection stock and block stock are not included in MRP run.
III)  Sales orders are not included in the MRP run.
IV)  Planned independent requirements are allowed for the material.
V)   Setting individual/collective indicator "1" may not be relevant for the material's components.

A)   I, III, V
B)   II, III, V
C)   I, III, IV, V
D)   II, V
E)   I, V
.