This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Sunday, January 27, 2008

Question no : 3 PP MRP Lot Sizing Rule

Determine the expected lot size calculated by MRP based on the following data:

  Current stock is 100 units
  MRP type is Re-order point
  Re-order quantity is 500
  Fixed Lot size is 300
  Satety stock is 200
  Rounding value is 50

A) 1 planned order of 400 units.
B) 1 planned order of 600 units.
C) 2 planned orders of 300 units each.
D) 3 planned orders of 200 units each.
E) 1 planned order of 200 units and another planned order of 300 units.
.

1 comment:

  1. Fixed Lot size always result in multiple supply MRP elements based the Fixed Lot size Quantity.

    ReplyDelete

Note: Only a member of this blog may post a comment.