Question: To show Simulation of Multi-Cycle Performance-Based Maintenance based on Engine Hours.
See the following Blog Post link for the detail presentation:
https://froggysap.blogspot.com/2024/09/sap-pm-multi-cycle-performance-based.html
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Question: The number 1-12 referring to Months of the Year, the 2 Technical Object which are Container 1 and Container 2 requires Monthly Maintenance as below:
Container 1: Preventive Maintenance is Month 1,2,3,4,5,6 and no need for Period 7-12
Container 2: Preventive Maintenance is Month 7,8,9,10,11,12 and no need for Period 1-6
And the same will repeat for the next year.
In SAP, the Maintenance Plan created for Monthly Cycle will always create MO for ALL Periods, the question is how to avoid scheduling any MO for Periods 7-12 for Container 1 as well as to avoid scheduling any MO for Periods 1-6 for Container 2.
Answer: Refer to the Blog Post link below for recommended Solution:
https://froggysap.blogspot.com/2024/09/sap-pm-fixed-and-skipped-status-use.html
--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------