Question no 3671 : Plant

In SAP MM as at ECC6.0 EhP6, which of the following scenario can be created without a Plant ?

(more than one answers)

A)  Create a Purchasing Info Record.
B)  Create an RFQ.
C)  Create a Contract.
D)  Create a Scheduling Agreement.
E)  Create a Source List.
.

Click on the "1 comment" to check possible Answers

1 comment:

  1. Answers: A, B, C

    Scheduling Agreement and Source List must be created with a Plant.
    While PIR, RFQ, and Contract can all be created without a Plant.

    ReplyDelete