Question no 3532 : Source List in MRP Run

In SAP MM and PP as at ECC6.0 EhP6, through the Source List, MRP run can do which of the following ?

(more than one answers)

A)  Assign a Vendor to the Planned Order.
B)  Create Purchase Requisition with assignment to a Vendor.
C)  Split the requirement to 2 sources of supply.
D)  Create a Purchase Order with assignment to a Vendor.
E)  Create Purchase Requisition with assignment to a Contract.
.

Answer: A, B, E

C) Split to multiple Vendor is a function of Quota Arrangement.