In SAP MM and PP as at ECC6.0 EhP6, through the Source List, MRP run can do which of the following ?
(more than one answers)
A) Assign a Vendor to the Planned Order.
B) Create Purchase Requisition with assignment to a Vendor.
C) Split the requirement to 2 sources of supply.
D) Create a Purchase Order with assignment to a Vendor.
E) Create Purchase Requisition with assignment to a Contract.
.
Answer: A, B, E
C) Split to multiple Vendor is a function of Quota Arrangement.
D) MRP Run do not create PO.
(more than one answers)
A) Assign a Vendor to the Planned Order.
B) Create Purchase Requisition with assignment to a Vendor.
C) Split the requirement to 2 sources of supply.
D) Create a Purchase Order with assignment to a Vendor.
E) Create Purchase Requisition with assignment to a Contract.
.
Answer: A, B, E
C) Split to multiple Vendor is a function of Quota Arrangement.
D) MRP Run do not create PO.