In SAP ERP  Quality Management as at ECC6.0, which of the following are true  when implementing Inspection Type '0130' inspection for external operation for production orders?

(more than one answers)

A)  Assignment of MIC to Routing operation is required.
B)  Use of Inspection Plan with appropriate Usage for the inspection type is possible.
C)  Assignment and activation of inspection type 0130 to material QM view.
D)  Assignment of inspection type to Routing operation with external operation control key is a must.
E)  Inspection lot is created when Production Order is released.
.

5 comments:

  1. A) MICs assigned to routing operation are valid for In-Process QC Inspection Type 03 for example and not for External Operation QM.

    ReplyDelete
  2. B) Inspection Plan is expected for this scenario unless RR is not needed.

    ReplyDelete
  3. C, D) You should activate inspection type 0130 at both material master QM view and assign it to the external operation in the routing.

    ReplyDelete
  4. E) Inspection lot is created when receiving the external operation PO.

    ReplyDelete