This Blog is mainly on SAP Exam Questions and Selected "How-to" SAP processes

Tuesday, March 23, 2010

Question no : 186 MM Purchasing Outline Agreement Basics

Which of the following is not true about outline agreements in MM ? 

I)    Both Contract and Scheduling agreement allows JIT and Forecast schedules.
II)   JIT schedule is always available but Forecast schedules is not for SA.
III)  Creation profile for SA are setup in the Purchasing view of the material master.
IV)  Delivery schedules are no longer available for SA document type LPA.
V)   Scheduling agreement can be created with reference to contract.

A)   I, II, IV.
B)   I, II, V.
C)   II, III, IV.
D)   I, II, III, IV.
E)   I, II, III, IV, V
.

1 comment:

Note: Only a member of this blog may post a comment.