Question no : 753 PM Preventive Components in Task List

PLM310 Preventive Maintenance
Unit 02 Management of Task Lists.

The following material components assignment is true for maintenance task list:
(more than one answers)

(A) To assign material components to a general maintenance task list, you must first enter an assembly in the general task list header.

(B) The material components that you want to assign to an equipment task list or functional location task list must be available in the respective bill of material when the assignment is made.

(C) The material components that you want to assign to an equipment task list or functional location task list do not have to be available in the respective bill of material when the assignment is made.

(D) No additional configurations are required to enable the free assignment of materials for maintenance task lists,

(E) It is possible to assign material components from the bill of material for the functional location/equipment or from the bill of material for subassemblies to task lists for functional locations/equipment.
.