Question no : 866 PM Execution Material Availability Check

PLM315 Maintenance Processing: Operational Functions
Unit 04 Scheduling

Material availability check is controlled by the:
(more than one answers)

(A) checking rule for the plant and order type.
(B) checking group for the plant and order type.
(C) checking group of the material component.
(D) checking rule of the material component.
(E) checking rule for the control key.
.