Thursday, December 2, 2010

Question no : 800 PM Preventive Plan Start Date Calculation

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

Estimated annual performance = 73,000 liters
Total number of days in a year = 365 days

For the data in the above question, assume that the initial counter reading is 10,000 liters and Cycle due at 60,000 liters; what is the expected planned start date ?
(only one answer)

(A) in 50 days.
(B) in 100 days.
(C) in 150 days.
(D) in 200 days.
(E) in 250 days.
.

Question no : 799 PM Preventive Expected Planned Start Date Calculation

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

Based on the following data, determined the expected planned start date (assuming the initial counter reading is 0) ?
(only one answer)

Estimated annual performance = 73,000 liters
Total number of days in a year = 365 days
Cycle due at = 40,000 liters

(A) in 730 days.
(B) in 365 days.
(C) in 200 days.
(D) in 100 days.
(E)  in 50 days.
.

Question no : 798 PM Preventive Call dates calculation

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

If the duration of the cycle is 250 days and the call horizon is either 0%, 80%, or 100% respectively; what are the call dates that the system creates for each call horizon scenario, the call date below is # days from the 1st day in the cycle duration ?
(only one answer)

(A) 0 day, 200 days, 250 days from the 1st day for each order respectively.
(B) 250 days, 250 days, 250 days from the 1st day for each order respectively.
(C) 0 day, 0 day, 0 day from the 1st day for each order respectively.
(D) 200 days, 200 days, 250 days from the 1st day for each order respectively.
(E) 0 days, 0 days, 250 days from the 1st day for each order respectively.
.

Question no : 797 PM Preventive Measuring Point Characteristics

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

In SAP PM ECC6.0, to implement Performance-Based Maintenance Plan, the following about measuring points/counter usage is not true ?
(more than one answers)

(A) You can use measuring points or measuring counters.
(B) You can use measuring counters only.
(C) Characteristics must be created first before it is assigned to create the Measuring Point in the Technical Object of Equipment and Functional Location.
(D) Measuring documents can be created directly in the technical objects.
(E) A characteristic is not necessary when you create the measuring points.
.

Question no : 796 PM Preventive Performance Based Plan Characterstics

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

Which of the following statements are true about Performance-Based Maintenance Plan ?
(more than one answers)

(A) It can only be created as a Single-Cycle Plan.
(B) It can be created as a Strategy Plan only.
(C) It can be created as a Single-Cycle Plan or a Strategy Plan.
(D) It can be created without using a Strategy Plan.
(E) It can be created as a Strategy Plan.
.

Question no : 795 PM Preventive Initialization of Measuring Point

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

The initial measurement document is the first measurement document that is entered for a newly added counter; the purpose of this initial entry is:
(only one answer)

_____ (A) It is automatically determined from the estimated annual performance entry in the counter; therefore manual entry is not required.
_____ (B) It is necessary as the maintenance plan cannot be started without an initial reading recording.
_____ (C) It represents the current counter reading at the time of the measurement counter.
_____ (D) It is not necessary as the maintenance plan is started with the estimated annual performance figure.
_____ (E) It provides the planned costs for the first maintenance order called.
.

Question no : 794 PM Preventive Annual Estimate

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

The purpose of the estimated annual performance is part of the counter is to:
(only one answer)

(A) form as the basis for calculating the maintenance intervals.
(B) form as the basis for cost estimate in the maintenance order.
(C) form as the basis for generating measuring documents for each maintenance order.
(D) form as the basis for estimating the operation time required for a specific time interval.
(E) form as the basis for calculating the planned cost in the maintenance order.
.

Question no : 793 PM Preventive Strategy Choice

PLM310 Preventive Maintenance
Unit 05 Maintenance Planning with Strategy: Performance-Based

If a inspection/safety check should be performed after 15,000 litres and all the seals changed after 200,000 liters, which of the following Preventive maintenance strategy is recommended ?
(only one answer)

(A) Time-Based Maintenance Planning Strategy.
(B) Performance-Based Maintenance Planning Strategy.
(C) Condition-Based Maintenance Planning.
(D) Sales-of-Service-Based Maintenance Planning.
(E) Single-Cycle Maintenance Planning.
.