In the standard plant maintenance system, using “PM05” control key as external work center processing would:
(more than one answers)

(A) create a purchase requisition automatically.
(B) uses confirmation instead of goods receipt for completing the operation.
(C) uses goods receipt to complete the operation.
(D) the activity price represent the hour rate offered by the external work center.
(E) purchase requisition is not created from the PM order.
.