Unit 03 Planning
The following work center header capacity data is for Question 17 and 18.
Start time 07:00:00
Finish time 17:00:00
Length of Morning Tea Break 00:15:00
Length of Lunch Break 00:30:00
Length of Afternoon Tea Break 00:15:00
Capacity utilization 60%
No of individual capacity 4 units
Calculate the available plant maintenance capacity for a work center with the following data:
(only one answer)
(A) 5.4 hours
(B) 24.0 hours
(C) 40.0 hours
(D) 36.0 hours
(E) 21.6 hours
.